Sisters High School Cost Sheet

(750 students)

Building costs $15,547,000

On-site costs

Site Prep $298,000

Site Utilities 554,000

On site improvements included in estimate

tennis courts with lights $126,000

Soccer/jv softball field 40,000

Soccer/jv baseball field 40,000

Varsity Softball 29,000

Varsity Baseball 31,000

60x100 basketball court 18,000

Basic performance football field 50,000

Courtyard and amphitheater 80,000

Bus loading/drop off 25,000

Visitor/staff parking 80,000

Student Parking (500 car) 200,000

Service and fire access road 110,000

Other improvements, landscaping, etc. 883,000

Total improvements in estimate $1,712,000

Total on-site costs$2,564,000

Off-site costs

(Upgrade McKinney Butte Road) $450,000

(Extend Sewer to Brooks Camp Rd) 70,000

Total Off-site Costs$520,000"Construction" costs $18,631,000

Other Construction costs

Contractor Overhead, Fee/Bond/Insurance $932,550

Escalation contingency 1%) 195,635

Design/estimating Contingency (5%) 987,960 Total "construction" costs$20,747,145

"Project" or "soft" costs

Professional Services

Architectural and engineering fees, on-site $1,426,250

Traffic Study 12,000

Site Survey 19,000

Geotechnical investigations 14,500

Inspection and Testing 22,500

Off-site fees 24,500

Total Professional Services $1,518,750

Licenses, fees, charges

Bid advertising/bid documents $15,000

Insurance 31,000

Legal fees 25,000

System Development charges (75 edu X $6,889/edu) 516,675

Building permits 54,000

Contingency (2 percent) 43,208

Total licenses, fees, charges $684,883Total "soft" costs"$2,203,633

High School Construction $22,950,778

Middle School Upgrades

Administration office: windows, carpet, paint $27,000

2nd floor classroom work 19,000

Remove and replace carpet 185,650

New outdoor basketball courts 16,000

Card entry system, new locks 14,000

Extend sewer from existing high school 20,000

Contingency (5% of above) 14,082

Pave Driveways (bid received, no contingency) 66,893

Architectural and engineering fees 25,000

Middle School SDCs (16 edu X $3994; could be 55 edu or $219,670) 64,000

Total Middle School Upgrades $451,625

Total High School plus Middle school $23,402,403

Options not in estimate

Performance football field features

(lights, fencing, sound, scoreboard) $270,000

Softball lights 24,000

Baseball field lights 30,000

Concession/restrooms 80,000

Greenhouse/van storage 190,000

Javelin facility 8,000

Discus at existing high school 6,000

Long jump at existing high school 11,000

Refinish floor at existing high school 36,000

Track resurface 120,000

Shot put at existing high school 8,000

Total options not in estimate $783,000

Total Project, with options $24,185,403

Possible deductions

Eliminate 2nd gym $639,000

Eliminate locker rooms 637,000

Reduce theater to 500 seats 295,000

Eliminate wrestling room 210,000

Eliminate outdoor recreation room 160,000

Eliminate plazas from classroom wing 207,000

Total Deductions$2,148,000

Total project, with options, less deductions $22,037,403Total project, no options, less deductions $21,254,403

Money available

Bond $20,500,000

Interest $1,900,000

Total money available $22,400,000

Proposed budgets

Reed/Lasken $22,400,000

Smith (plus $450,000 for middle school) $21,450,000

Wester/Keeton $20,500,000

 

Reader Comments(0)